Saturday, September 29, 2012
Week 10
Day 70 - Wood framing around windows, framed arch above front door and vapor barrier, chicken wire up and scratch coat started for rock. |
Day 70 - Entryway sheet-rocked. |
Day 70 - Living room and dining room sheet-rocked. |
Day 70 - Kitchen sheet-rocked. |
Day 70 - Sheetrock, planter shelf in living room and part of kitchen. |
Day 70 - Hall sheet-rocked. |
Day 70 - Other front bedroom sheet-rocked. |
Day 70 - Front bedroom sheet-rocked. |
Day 70 - Sheetrock, planter shelves in master bedroom. |
Day 70 - Sheetrock master bedroom. |
Day 70 - Sheetrock laundry room. |
Week 9
Day 65 - Shingles are on the roof. |
Day 62 - Master bedroom insulation. |
Day 62 - Other front bedroom insulation. |
Day 62 - Front bedroom insulated. |
Day 62 - More basement insulation. |
Day 62 - Basement with insulation. |
Day 62 - The right door and more insulation. |
Day 62 - More insulation. |
Day 62 - Insulation blown in. |
Day 62 - Rough plumbing. |
Day 62 - Rough electrical. |
Week 8
Day 55 - They finished the wrap on the outside of our house. |
Day 55 - Living room windows and sliding glass door in dining room. |
Day 55 - They also installed our tubs. This is the master bathroom tub. |
Day 55 - Other front bedroom window. |
Day 55 - They installed out windows (font bedroom window) |
Day 55 - The door from the garage into the kitchen. |
Day 55 - This is our front door (well technically they installed the wrong one but it will look kind of like this but with a window in it) |
Day 55 - Water heater and furnace installed. |
Sunday, September 9, 2012
Week 7
Day 48 - Framing Finished (Completed Trim on the Outside) |
Day 48 - Interior (Part of Kitchen - Pantry) |
Day 48 - Interior (Laundry Room) Creates a cool planter shelf in the living room. |
Day 47 - Back & Side of House |
Day 47 - Finished Roof Sheeting |
Day 46 - Roof Sheeting |
Day 45 - Trusses |
Day 45 - Trusses / Roof |
Friday, August 31, 2012
Week 6
Day 41 - Finished Exterior Framing (the trusses are in the right corner of the pic so hopefully that means the roof will go up soon!) |
Day 41 - Finished Exterior Framing (View of the back/side of the house) |
Day 40 - Main Floor Interior Framing |
Day 40 - Main Floor Interior Framing |
Day 40 - Main Floor Interior Framing |
Day 40 - Main Floor Interior Framing |
Day 39 - This is the day we we had been waiting for....it finally went vertical! Main Floor Exterior Framing. |
Day 38 - Basement Framing and Sub-floor |
Sunday, August 26, 2012
The Beginnings of a House