Saturday, September 29, 2012

Jordan & Katie's Rooms





Week 10

Day 70 - Wood framing around windows, framed arch above front door
and vapor barrier, chicken wire up and scratch coat started for rock.


Day 70 - Entryway sheet-rocked.


Day 70 - Living room and dining room sheet-rocked.


Day 70 - Kitchen sheet-rocked.


Day 70 - Sheetrock, planter shelf in living room and part of kitchen.


Day 70 - Hall sheet-rocked.


Day 70 - Other front bedroom sheet-rocked.


Day 70 - Front bedroom sheet-rocked.


Day 70 - Sheetrock, planter shelves in master bedroom.


Day 70 - Sheetrock master bedroom.


Day 70 - Sheetrock laundry room.


Week 9

Day 65 - Shingles are on the roof.


Day 62 - Master bedroom insulation.


Day 62 - Other front bedroom insulation.


Day 62 - Front bedroom insulated.


Day 62 - More basement insulation.


Day 62 - Basement with insulation.


Day 62 - The right door and more insulation.


Day 62 - More insulation.


Day 62 - Insulation blown in.


Day 62 - Rough plumbing.


Day 62 - Rough electrical.

Week 8


Day 55 - They finished the wrap on the outside of our house.


Day 55 - Living room windows and sliding glass door in dining room.


Day 55 - They also installed our tubs. This is the master bathroom tub.


Day 55 - Other front bedroom window.


Day 55 - They installed out windows (font bedroom window)


Day 55 - The door from the garage into the kitchen.


Day 55 - This is our front door
(well technically they installed the wrong one but it
will look kind of like this but with a window in it)


Day 55 - Water heater and furnace installed.


Day 52 - House wrap and they put the shingles are
on the top of the roof waiting to be installed.

Sunday, September 9, 2012

Week 7

Day 48 - Framing Finished (Completed Trim on the Outside)


Day 48 - Interior (Part of Kitchen - Pantry)


Day 48 - Interior (Laundry Room)
Creates a cool planter shelf in the living room.



Day 47 - Back & Side of House


Day 47 - Finished Roof Sheeting


Day 46 - Roof Sheeting


Day 45 - Trusses


Day 45 - Trusses / Roof

Friday, August 31, 2012

Week 6


Day 41 - Finished Exterior Framing (the trusses are in the right
corner of the pic so hopefully that means the roof will go up soon!)


Day 41 - Finished Exterior Framing 
(View of the back/side of the house)


Day 40 - Main Floor Interior Framing


Day 40 - Main Floor Interior Framing


Day 40 - Main Floor Interior Framing


Day 40 - Main Floor Interior Framing


Day 39 - This is the day we we had been waiting for....it 
finally went vertical! Main Floor Exterior Framing.


Day 38 - Basement Framing and Sub-floor

Sunday, August 26, 2012

The Beginnings of a House


Day 36 - Garage Slab


Day 36 - Basement Floor


Day 31 - Backfill and Rough Plumbing


Day 22 - Foundation


Day 20 - Forms for Foundation


Day 19 - Footings (Garage)


Day 19 - Footings


Day 18 - Ladies and Gentleman...We Have a Hole!!!


Day 1 - The Chosen Lot